Complete the Upgrade Process (Only When S8300 is Primary Controller)�

Check Media Modules

Begin _____________________

  1. Type list configuration all and press Enter.
  2. Verify that the software is communicating with all media modules and that all media modules are listed in the reports.
  3. Make test telephone calls to verify that MultiVantage Software is working.

Enable Scheduled Maintenance

Begin _____________________

  1. Type change system-parameters maintenance and press Enter.
  2. Ensure that the Start Time and Stop Time fields' administration is the same as before the upgrade.

Enable TTI

Begin _____________________

Note: Perform this step only if you disabled TTI before the upgrade.

  1. Type change system-parameters features and press Enter to change the TTI field back to its value before the upgrade.
  2. Go to the second page and set the Terminal Translation Initialization (TTI) Enabled? field to y and press Enter.

Check TTI Status

Begin _____________________

  1. Type status tti and press Enter.
  2. Check the Percent Complete field.

If the value is 100, then go on to the next section.

If the value is less than 100, repeat Steps 1 and 2 until the Percent Complete field is 100.

Busy Out Trunks

Begin _____________________

  1. Busy out trunks that were busied out before the upgrade (see Record All Busyouts).

Resolve Alarms

Begin _____________________

  1. Click View Current Alarms to examine the alarm log.
  2. Resolve new alarms since the upgrade through the MultiVantage Software using the appropriate maintenance book.

Check for Translation Corruption

Begin _____________________

  1. Type newterm and press Enter.

If you do not get a login prompt and see the following message:

Warning: Translation corruption detected

follow the normal escalation procedure for translation corruption before continuing the upgrade.

Back up the System

Begin _____________________

  1. Back up the system as you did before the upgrade.