In what order do I power down and power up the cabinets in high and critical reliability systems? Does it really matter?
It is not necessary to power down the EPN to do an upgrade. (If the EPN is remote, you may not even know where it is.) The order doesn't matter for power-down, but it does for power-up. If you did power down the EPN cabinet, power up it first, then power up the PPN cabinet.
Always power up the control cabinet last.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |