Power Up System (DS1 Tie and OPS Trunks)

Return to Task List

  1. At each EPN, set the main circuit breaker to ON.

  2. At the PPN, set the main circuit breaker to ON.

  3. The system performs the level 4 rebooting process, loading the system translations from the translation card or removable media. Rebooting takes 8 to 11 minutes.

  4. After the system reboot is finished and all trouble is cleared, verify that the EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores the system to the normal mode.

Return to Task List