DEFINITY Made Easy Tools
Issue 2, November 2000
Install Additional Hardware
Power Up System
- At the EPN, set the main circuit breaker to ON.
- At the PPN, set the main circuit breaker to ON.
- The system performs a level 4 reboot, loading the system translations from the translation cards. Rebooting takes about 10 minutes.
- After all trouble is cleared, verify the EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores the system to the normal mode.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Copyright� 2000 Avaya Inc |
Send comments to MadeEasy Development Team |
Always check at the Made Easy Web site for the most current information. |