DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for R9 Go to Installation for MCC Go to Installation for SCC



Perform Complete System Test

Return to Task List

Run the complete system test with the "Allports" option in the "SPE Interchange" and "Long Test" modes. The hardware group tests are described in DEFINITY Enterprise Communications Server Release 8 Maintenance for R8r or DEFINITY Enterprise Communications Server Release 8 Maintenance for R8si.


Note: This test takes several hours. It may be best to run the test in the background, or at night, or both.


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for R9 Go to Installation for MCC Go to Installation for SCC
Copyright 2000 Avaya Inc
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.