DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for R9 Go to Installation for MCC Go to Installation for SCC



UPS Installation for SCC EPN A-Carrier Cabinet

This section describes the procedure for connecting the Lucent Series 1 On-Line Uninterruptible Power System (UPS) to a DEFINITY ® SCC EPN cabinet. The UPS maintains critical A-carrier ports for about 14 minutes during a power outage. It also provides information on wiring, administering, and documenting alarms, which allows remote monitoring of power and UPS problems.

There are two configurations for connecting a UPS to an SCC cabinet:

Task List: Install UPS

  1. Connect the UPS

  2. Wire the 700A8 Plug

  3. Make the Remaining Connections

  4. Administer the External Device Alarm (EDA)

  5. Load-test and Verify Alarms


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for R9 Go to Installation for MCC Go to Installation for SCC
Copyright 2000 Avaya Inc
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.