DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC



Power Up System (Packet Bus Support)

Return to Task List

  1. At the EPN, set the main circuit breaker to ON.

  2. At the PPN, set the main circuit breaker to ON.

  3. The system performs a level 4 reboot, loading the system translations from the translation cards. Rebooting takes about 10 minutes.

  4. After all trouble is cleared, verify the EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores the system to the normal mode.

Return to Task List


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC
Copyright 2001 Avaya Inc.
Send comments to MadeEasy Development Team