Installation for MCC Made Easy

Perform these tasks to install multicarrier cabinets:

  1. Install and Connect Multi-Carrier Cabinets

  2. Install Telecommunications Cabling

  3. Bring the System Online

  4. Test the System

  5. Install and Wire Telephones

  6. Install and Administer Trunks

  7. Install and Wire Telephone Power Supply

  8. Install Additional Hardware

  9. Add IP Solutions

  10. Install and Connect Modems

  11. Administer the features, telephones, and other equipment according to customer data found on the provisioning plan. Use the procedures in the DEFINITY Enterprise Communications Server Administrator's Guide.

  12. Test Telephones and Other Equipment

Select the activity you are currently performing to see information, task lists, and procedures for that activity.


Note: It may be more efficient to install each hardware component, administer it, and test it before going on to install another component. As an example, install the attendant console using the procedures in Install and Wire Telephones, administer it using the procedures in the DEFINITY Enterprise Communications Server Administrator's Guide, and test it using the procedures in Test Telephones and Other Equipment.

You can also find information on these topics here:


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC
Copyright 2001 Avaya Inc.
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.