Position the PPN Cabinet
- If the system is supplied with cable ductwork, space the cabinets on 32 in. (81.3 cm) centers +-1/8 in. (0.3 cm). They must be level and must be square with respect to each other.
- If the system is supplied with cable slack managers, place the cabinets far enough from the connection field to lay down the 32 in. (81.3 cm) slack managers and to provide a little extra room for the cables to access the cable slack managers.
- If earthquake protection is required, Install Earthquake Protection for MCC.
- If earthquake protection is not required, level the cabinets and adjust and lock the cabinet stabilizing bolts to keep the cabinet from moving.
- At the bottom of the cabinet, install hole plugs (provided with cabinet) in the holes previously occupied by the 4 carriage bolts.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |