Power down cabinet(s) [R10si]

Return to Task List


Note: Before powering down the cabinet(s), make sure you have all replacement circuit packs and new ATA flashcards nearby to minimize down time.


Caution! Important system data such as BCMS data, records of queued ACD calls, Automatic Wakeup requests, and Do Not Disturb requests will be lost on power down. You cannot store to or retrieve data from tape or flash.


Caution! On a DC-powered SCC, do not power down by reseating the power supply as it will trip the breakers on the DC power cabinet.


Note: The breaker on an MCC is on the bottom front of the cabinet; the breaker on an SCC is on the back of the cabinet.

  1. At the PPN power-distribution unit, set the main circuit breaker to OFF.

  2. If the site has a power-failure transfer panel, connect a ground strap to the panel and to a ground source. Verify that the power-failure stations are working.

  3. Remember to disconnect this strap before reapplying power.

Return to Task List


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC
Copyright 2001 Avaya Inc.
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.