Releasing the Switch Data Link
Important! This task applies only to DEFINITY switches. If the customer does not have a DEFINITY switch, do not use this task and go to the next task, Verifying the Cable Connections.
For this procedure, DEFINITY switches are divided as follows:
- Releasing the Data Link on a System 75 G1 or G3 Switch
- Releasing the Data Link on a G2 Switch
- Releasing the Data Link in an OverLAN Integration
Releasing the Data Link on a System 75 G1 or G3 Switch
To release the data link on a System 75 G1 or G3 switch, perform the following tasks on the switch administration terminal (SAT):
- Enter release link n
where n is the number of the link going to the Avaya Intuity system. Valid input is an integer from 1 to 8.
For more information, see the DEFINITY switch documentation.
- Continue with the next task, Verifying the Cable Connections.
Releasing the Data Link on a G2 Switch
To release the data link on a G2 switch, perform the following tasks on the switch administration terminal (SAT):
- Enter proc650 test 3
- Enter rb
For more information, see the DEFINITY switch documentation.
- Continue with the next task, Verifying the Cable Connections.
Releasing the Data Link in an OverLAN Integration
To release the data link in an OverLAN switch integration, perform the following tasks on the switch administration terminal (SAT):
- Enter ch com p
- Locate
Intuity AUDIX
in theNode
column.- Press the DOWN ARROW key to the
Intuity AUDIX
field.- Enter y
The system displays the following message:
Command successfully completed.- Continue with the next task, Verifying the Cable Connections.