Two 7254s (core switches) connected by vIST. Attempting to connect a stack of 3549s with redundant 10G fiber links (SLT). However, when I power up these 4 devices, only one of the uplinks comes up.
Cores 1 & 2
mlt 1 enable name "MLT_IDF1"
mlt 1 member 1/1
mlt 1 encapsulation dot1q
!
interface mlt 1
smlt
exit
Edge Stack
mlt 1 name "ToCore" enable member 1/49,2/49
!
vlan ports 1/49,2/49 tagging tagAll
!
interface Ethernet ALL
spanning-tree port 1/49 learning disable
spanning-tree port 2/49 learning disable
exit
!
mlt 1 learning disable
Have checked all layer 1, known good cables, known good SFP+. Can't figure out why the redundant link will not come up. Please help!
Cores 1 & 2
mlt 1 enable name "MLT_IDF1"
mlt 1 member 1/1
mlt 1 encapsulation dot1q
!
interface mlt 1
smlt
exit
Edge Stack
mlt 1 name "ToCore" enable member 1/49,2/49
!
vlan ports 1/49,2/49 tagging tagAll
!
interface Ethernet ALL
spanning-tree port 1/49 learning disable
spanning-tree port 2/49 learning disable
exit
!
mlt 1 learning disable
Have checked all layer 1, known good cables, known good SFP+. Can't figure out why the redundant link will not come up. Please help!
Comment