    Hi,

    Visual vectors upgrade in R16.3 ( baseload upgrade) in a HA scenario:
    Base load upgrade has been already done,but visual vector software needs to be upgraded.current version of VV is 16aa.c. So.I'm wondering...

    When the VV upgrade is done on each primary and secondary upgrades separately ,
    since the VV changes are administrative data,will it be a good procedure to upgrade the secondary and later upgrade primary( may be a week later) and sync this missing administrative data from secondary to primary,when both the CMS servers are on the same new visual vector software?

    Thank you.
  • shaikht
    Genius
    .
    • Feb 2010
    • 246

    #2
    Hi,

    I like your approach but still want that all administrative stuff should be done on primary. Once HA is upgraded with new VVS, it need to be sync with Primary CMS. So Admin sync will be from primary to Ha rather than Ha to primary.

    I hope it helps.