Hi!
Is the first time that I am configuring the Virtual (Ghost) IP Network Region.
May you help me to understand if my configuration are correct or not?
The environment has five Locations.
All ip-interface (TN2602 and TN799CP) are assigned to the IPNR 250.
C.M is configured to respond over PROCR!
IPSI and Media Resource are configured in duplicated mode.
In the attached file VIPNR.TXT, are the configuration of "ip-network-region" form of page 3 - "Inter Network Region Connection Management".
I have some doubts:
Should I assign the Media Resource to the IPNR 250?
Do I need to define limits to the IPNR-1 destination on the IPNR-250 or leave without them?
Must the end-points' of location 2 to 5 register at the PROCR?
What is the best proposal of AGL to my scenario?
Is the first time that I am configuring the Virtual (Ghost) IP Network Region.
May you help me to understand if my configuration are correct or not?
The environment has five Locations.
- Location 1 - Main Location;
- Communication Manager 5.2.1;
- Media Server S8730 with hardware duplication;
- Two (02) Media Gateways G650;
- Cabinet A
- 01 IPSI TN2312BP - 01A01;
- 03 CLANs TN799CP - 01A02 to 01A04;
- 01 Media Resourse TN2602AP 320 - 01A14;
- 01 VAL Announcement TN2501AP - 01A07;
- 01 Maintenance TN771DP - 01A08;
- 02 DS1 TN2464CP- 01A12 and 01A13;
- Cabinet B;
- 01 IPSI TN2312BP - 01B01;
- 02 CLANs TN799CP - 01B02 and 01B03;
- 01 Media Resourse TN2602AP 320 - 01B14;
- 02 DS1 TN2464CP - 01B013;
- Cabinet A
- Location 2 to 5
- Media Gateway G450;
- 01 S8300D as LSP;
- Media Gateway G450;
All ip-interface (TN2602 and TN799CP) are assigned to the IPNR 250.
C.M is configured to respond over PROCR!
IPSI and Media Resource are configured in duplicated mode.
In the attached file VIPNR.TXT, are the configuration of "ip-network-region" form of page 3 - "Inter Network Region Connection Management".
I have some doubts:
Should I assign the Media Resource to the IPNR 250?
Do I need to define limits to the IPNR-1 destination on the IPNR-250 or leave without them?
Must the end-points' of location 2 to 5 register at the PROCR?
What is the best proposal of AGL to my scenario?
Comment