    Hi.

    I'm new with Avaya (S8300). So I have now one problem, how to change vector in many vdn. Can I do this with some script (now I'm doing this with Avaya Site Administration).

    /Tomek
  • sunilkumarv
    Guru
    .
    • Mar 2010
    • 124

    #2
    hello,

    you can always use export/Import options in Site administration , export the vdn data , correct the vector numbers using excel. then import it with change command.
    Regards,
    Sunil

    AVAYA| Voice: US:- +1 720 444 5271, India: +91 80 6715 3277 | Email:[email protected]|

    Comment

    • ena
      Aspiring Member
      • Dec 2014
      • 1

      #3
      I also encountered similar problems

      Comment

      • marzahn
        Genius
        • May 2014
        • 236

        #4
        Three Optional Approaches

        Originally posted by w2 View Post
        Hi.

        I'm new with Avaya (S8300). So I have now one problem, how to change vector in many vdn. Can I do this with some script (now I'm doing this with Avaya Site Administration).

        /Tomek


        The export/import works just fine. Morover going forward there are three other ways to approach this:
        • Use the "duplicate vector" command to create multiple new vectors from one "Master" vector.
        • Use the "change variables" commend to use the Varialbles for Vectors table.
        • Use VDN varialbles to customize a single vector for multiple use.
        Your selection depends on what you are trying to do. There is a lot of power available to you in these three.
        Thank you,