Return to Task List

  1. Set the associated circuit breakers on the AC power panel ON.


Note: If the system is high or critical reliability, power-up the Expansion Port Network (EPN) first, then the Processor Port Network (PPN). Always power up the control cabinet last.

  1. At the rear of each cabinet, set the circuit breaker to ON. This starts the system initialization and test. Some red lights may be on but will be turned off by other procedures in this chapter.