DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC



Retranslate port circuits [75 XE upgrade]

Return to Task List

  1. If port circuit packs in the R1V3 control cabinet were relocated, verify that they were retranslated during the off-site software upgrade.

  2. If they were not retranslated, you must retranslate them now.

  3. Refer to DEFINITY Enterprise Communications Server Administrator's Guide for instructions on performing the retranslations.

Return to Task List