Verify the upgrade [R9si]

Return to Task List

  1. Execute status system [option] and verify that the system is in a normal state.

  2. Type display alarms and press Enter.

  3. If the system is not alarm-free, take the needed corrective actions.

  4. Type list conf soft (simplex) or list conf soft long (duplex) and press Enter. Verify the software configuration.

  5. Type display comm links and press Enter.

  6. Status each of the links.


Note: ISDN-PRI D-channel links no longer appear on this screen. (For release 7 and later, ISDN-PRI resides on the network packet circuit pack.) For release 7 and later, the only way to determine if an ISDN-PRI D-Channel is up is to use the status signaling group command.

  1. Type list signal press Enter. For each signal, execute status signal < number>.

  2. Validate that all the signal groups that should be operational are in-service.

  3. Execute the following commands and verify that the information is correct:

  4. list stations

    list trunks

    list hunt groups

    list data

    For upgrades from systems later than G1, list ars analysis

    For a system with Expert Agent later than G3V3, list agent

  5. For duplicated systems only, execute status system 1

Return to Task List


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for R9 Go to Installation for MCC Go to Installation for SCC
Copyright 2000 Avaya Inc
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.