DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC



Run acceptance tests [G3V4 to R10si]

Return to Task List

Run any acceptance tests that are appropriate for this upgrade. The acceptance tests are listed in these 3 checklists:

Test single-carrier cabinet systems

Test multi-carrier cabinet systems

Test telephones and other equipment

For details of the tests, see

Test the System

Test Telephones and other Equipment

Test single-carrier cabinet systems

  1. Check System Status for Each Cabinet

  2. Check Circuit Pack Configuration

  3. Test Time Division Multiplexing Bus in Processor Port Network

  4. Test Tone-Clock Boards

  5. Test Expansion Interface Circuit Packs

  6. Test Time Division Multiplexing Bus for Each Expansion Port Network

  7. Test Tone-Clock for Each Expansion Port Network

  8. Test Tone-Clock Interchange for Each Expansion Port Network

  9. Test Expansion Interface Exchange for Each Expansion Port Network

  10. Check Circuit Pack Configuration

  11. Save Translations, if Required

Test multi-carrier cabinet systems

  1. Check System Status for Each Cabinet

  2. Check Circuit Pack Configuration

  3. Test TDM Bus in PPN

  4. Test Tone-Clock Circuit Packs

  5. Test SPE Duplication Memory Shadowing Link

  6. Test Duplicated Switch Processing

  7. Element Interchange

  8. Test Expansion Interface Circuit Packs

  9. Test TDM for each EPN

  10. Test Tone-Clock for each EPN

  11. Test Tone-Clock Interchange for each EPN

  12. Test Expansion Interface Exchange for Each EPN

  13. Check Circuit Pack Configuration Again

  14. System Test Completion

  15. LED Indicators

Test telephones and other equipment

  1. Make Test Calls

  2. Test 302C Attendant Console

  3. Test External Ringing

  4. Test Queue Warning Indicator

  5. Test Integrated Announcement

  6. Test Music-on-Hold

  7. Test Emergency Transfer

  8. Test Remote Access Interface

  9. Test Basic Rate Interface

  10. Test Duplication Option Processing

  11. Element Interchange

  12. Test Terminating Trunk Transmission

  13. Test Stratum 3 Clock

  14. Perform Complete System Test

  15. Activate and Test Alarm Origination Feature

Return to Task List


DEFINITY Made Easy Home Page Table of contents Previous page Next page Index Links Frequently asked questions
Go to Upgrades for si Go to Installation for MCC Go to Installation for SCC
Copyright 2001 Avaya Inc.
Send comments to MadeEasy Development Team



Always check at the Made Easy Web site for the most current information.