System Installation Checklist

This installation checklist provides descriptions of the required procedures, in sequence, to use when you install an assembled, loaded, and tested (ALT) Avaya INTUITY AUDIX LX system. You can use the Installation Printable Guide for the INTUITY AUDIX LX (pdf) that includes all of the first-time installation processes in order.

Note: If you need to install a feature for the customer on an ALT system, contact your project manager to verify the requirements and contact your remote support center.

 

The following table provides a checklist for the system installation including integration with most switches.

 

Task Description Comments and Screens
1. Review Installation Planning and Prerequisites.

This section includes:

       
2. Gather the required tools.    
3. Verify that the switch has been administered in preparation for the new system. See the switch administrator. Required switch administration is listed in Initial Switch Administration.  
4. Determine if you need to notify the LAN administrator to arrange for administration of the LAN for the system.

Note: Avaya is not responsible for the installation, administration, or test of communications between customer PCs and the LAN.

See the LAN administrator.

Note: Some LANs may be administered prior to your arrival on site. Other LANs require that the administration for a new machine be done at the time of installation because an open connection may cause the LAN to fail.

 
5.
All systems, application dependent.
 
6.
Review Security issues.
All systems.
 
7.
Open boxes as instructed to reuse packing materials.
 
8. Place the chassis in the designated operating area. Ensure sufficient airspace around it and turn the stabilizing feet out to the side. Note: If stabilizing feet have not been installed, use a Phillips screwdriver to fasten the 4 stabilizing feet to the bottom of the chassis.  
9. Connect Peripheral Devices. This includes monitor, keyboard, and modem.  
10. Connect the Analog-line Interface Cards (voice cards).    
11. Connect the LAN cable.    
12. Restore Power to the System.    
13. Check Voice System, Modem, and Network Addressing.
  • System Status
  • Install Modem/Terminal Software
  • Network Addressing
 
14. Load Language Packages. This is optional, depending on customer preference.  
15. Load Switch Integration Software.
  • Install Software
  • Switch Selection
 
16. Administer the Switch Integration. If additional administration is needed, reference the applicable Switch Integration procedures.  
17. Perform Initial System Administration. Follow the Initial System Administration procedure for a complete listing of pages and screens to be completed.  
18. Activate Alarm Origination. Enter the phone number that receives alarm notifications.  
19. Perform System Acceptance Testing.    

 